REFERENCE LIST

 

 

 

Back

Summary of larger projects at sea                                                        

                                                                                          

 

Place

 

 

Description of project 

 

Year 

 

Customer 

 

Duration

 

Amrumbank West

OWF Germany

 

Main contract for delivery and installation of filled geotextile bags serving as a scour protection around 80 WTG foundations.

Total amount 30,720 bags = 41,500 t

2012/13

 

E.On

 

  16 months

  ongoing

 

Aarhus

Denmark

 

Maintenance dredging of habour, hereunder survey and documentation.

Total amount: 63,000 m3

Depth: -10/-14 m

2012/13

 

Port of Aarhus

 

  8 months

  ongoing

 

Avedøre

København

Denmark

 

Maintenance dredging of area in front of two cooling outlets on a CPH plant, hereunder reclaimation of all material dredged.

Total amount: 11,200 m3

Depth: -2 m

2012/13

 

DONG Energy

 

  4 months

  ongoing

 

Moray

UK

 

Maintenance dredging of 3 harbours and approach channels.

Total amount: 14,890 m3

Depth: -0,6 & -3,0 & -3,3 m (CD)

2012

 

Moray Council

 

  1 1/2 months

 

Mariager Fjord

Denmark

 

Delivery and placement of 3,8 km Ø800 PE100 pipe, hereunder trenching, ballasting, placing, testing, backfilling and survey and documentation.

2012

 

Mariagerfjord Vand A/S

 

  3 months

Oslo

Norway

Dredging of contaminated material from ferry berth and transporting 26 Nm to land fill. Work was continously monitored for tubidity.

Total of 6,000 m3 dredged

2012

AK Construction

  1 month

Port ellen

Scotland, UK

 

Dredging of Harbour basin and ferry berth.
Total of 15,000 m3 dredged
Placing of scour protection in ferry berth approx. 5,000 m3

2012

McLaughlin & Harvey Ltd

 

2 months

 

Port ellen

Scotland, UK

 

Dredging of Harbour basin and ferry berth.
Total of 15,000 m3 dredged
Placing of scour protection in ferry berth approx. 5,000 m3

2012

McLaughlin & Harvey Ltd

 

2 months

 

Kalundborg

Denmark

 

Dredging of approach channel to  an oil pier. Included dredging, transportation to offshore dumping site and dumping through environmental silt curtain.
Total amount: 65,000 m3
Depth: -15,0 m

2011/2012

Statoil Refining

Denmark

3 months

 

Anholt OWF

Denmark

 

Glacial dropstone boulder relocation from turbine positions and cable routes prior to installation. The boulders collected being placed in reef-like structures to form new marine wildlife habitats within the Wind Farm area
Total amount approx. 7.200 boulders

2011/2012

Dong Energy

6 months

in progress

 

Pori

Finland

 

Boulder removal in connection with major dredging works of the navigation channel to Mäntyluoto.
Total amount approx 450 boulders

2011

Van Oord

1 months

 

Kirkwall, Strongsay & Lyness

Orkney Islands

 

Dredging, transportation and dumping offshore of sand from navigation channel and harbours.
Total amount: 25,000 m3
Depth: -3.5m

2011

Orkney Island Council

3 months

 

Udbyhøj 

Denmark

 

Dredging of approx. 13,000 m3 of sand in connection with establishment of new Marina, hereunder; transportation 12 Nm and pumping on-shore.

2011

CG Jensen

Denmark

1 months

 

Nibe

Denmark

 

Maintenance dredging of navigation channel to Nibe. 
Quantity: 10,000 m3.
Material: sand
Depth: -2.50m

2011

2009

2008

2007

Aalborg Kommune

Teknik- og

Miljøforvaltning

denmark

1 months

 

Wendtorf Marina

Germany

 

Maintenance dredging of the Marina.
Total amount: 12.000 m3
Material: Sand

2011

ShipShape

Marina Wendtorf

Germany

1 months

 

Schlien

Germany

 

Dredging from 3 places along the Schlien channel to Schleswig. Dredging work was retricted due to two low bridges.
Total amount approx 5.600 m3

2011

Wasser - und

Schiffahrtsamt Lübeck

1 months

 

Wismar

Germany

 

Maintenance dredging in Wismar hereunder dredging of underwater deposit areas for contaminated silt and leveling of seabed.
Total amount approx. 5.500 m3

2011

Inros Lackner AG

Germany

1 months

 

Frederiksværk

Denmark

Trenching, placing and backfilling for 3x132 kV, 3x50 kV and fibre optic cables for establishing new power supply to steel mill. Hereunder extra depth in fairway and floating channel for aproaching the shore.

2011

Vorksla Steel

Denmark A/S

1 months

 

Tahkoluoto

Finland

Maintenance dredging in Coal terminal in Tahkoluoto, Finland.

Depth: -17,5 m.

2010/2011

Porin Satam

Finland

1 months

 

NordStream

Germany

Re-establishment of stone reef over Gas-pipe trench.
Total amount approx 25,000 ton reclaimed at dumpsite.
Including Multi beam survey and side scan survey of an area of 152,000 m2

2010/2011

NordStream AG

Switzerland

1 months

 

Riga Latvia

Maintenance dredging of harbour.

Quantity: 25,000 m3.

Depth: -11,0 m.

2010

Rohde Nielsen A/S

Denmark

2 months

 

Pori Finland

Boulder removel in coonection with mayor dredging works of the navigation channel to Mäntyluoto.

Total amount approx 2000 dropstons.

2010

Van Oord

3 months

 

Vyborg

Russia

Boulder removel within a corridor of 35 m x 7000 m in order to clear the way of the Nordstream gas pipeline between Russia and Germany.

Total amount approx 135 boulders.

2010

Van Oord

1 months

 

Rødsand 2 OWF

Denmark

Delivery and placement of round stones 200/700mm from land to be placed around 18 foundations serving as collision protection.

Quantity: 6,500m3 Total turn over – Euro 945,000.-

2010

E.ON Vind

4 months

Kontek Cable, Baltic Sea,

Denmark

Trenching and backfilling of 12.6 km 400 kV sea cable for export of power between Denmark and Germany

Total turn over – Euro 2,580,000.-

2010

Energinet.dk

7 months

Baltic 1 OWF

Germany

Delivery and placement of scour protection (filter & armour stones) of 21 foundations including surveys.

Total turn over – Euro 2,990,000.-

2010

EnBW Systeme Infrastruktur Support GmbH

4 months

Dasser Ort Germany

Dredging and transportation of sand

Quantity: 50,000 m3

Discharged at sea, distance 4 Nm

Depth: -3.5 m

Total turn over – Euro 600,000.-

2009/10

Straßenbauamt Stralsund

 

5 months

Øer Maritime

Ferieby

Denmark

Maintenance dredging

Material: Sand

Quantity: 10,000 m3

2009

Mogens de Linde

Denmark

1 months

Sprogø Denmark

Sprogø offshore wind farm.

Placing of Scour protection and Ballast on the 7 wind mils foundations.

Total turn over – Euro 850,000.-

2009

Joint Venture

Aarsleff / Bilfinger

1 months

Robin Rigg

OWF

England

Robin Rigg Offshore Wind Farm.

Placing of Scour protection around 13 monopiles in water depths up to 14m.

Total turn over – Euro 940,000.-

2009

MT Højgaard

Knud Højgaards

Vej 9

DK-2860 Søborg

5 months

Sprogø Denmark

Sprogø offshore wind farm. Trenching, laying and backfilling of cables between windmills and to the coast of Sprogø.

Total turn over – Euro 2,200,000.-

2009

Sund og Bælt A/S

3 months

Rødsand 2 OWF

Denmark

Placing of Scour protection and ballast on 90 foundations for the wind mils.

Total turn over – Euro 2,450,000.-

2009

Joint Venture

Aarsleff / Bilfinger

Project in progress

10 months

Rødsand 2 OWF Denmark

Trenching and backfilling of 8 km 132 kV sea cable for Rødsand 2 offshore wind farm to the coast of Lolland

Total turn over – Euro 1,000,000.-

2009

Energinet.dk

7 months

Rødsand 2 OWF

Denmark

Trenching and backfilling of 70 km sea cable for Rødsand 2 offshore wind farm between the windmills.

Depth: -6 to -14 m

Total turn over – Euro 6,100,000.-

2008/09

E-on

Project in progress

18 months

Hornsrev 2 OWF

Denmark

Repair of scour protection near the monopile

Depth 10-16m LAT

Total turn over – Euro 500,000.-

2008

JV Aarsleff/ Bilfinger

4 months

Esbjerg Denmark

Jetting of sea cable on the west coast of Denmark.

Total turn over – Euro 400,000.-

2008

Denholm offshore Ltd.

 

3 months

Leixões,

Portugal

07.097/136

Dredging and transportation of blasted rock

Quantity: 100,000 m3

Discharged at sea, distance 2 Nm

Depth: -9 m

Total turn over – Euro 1,500,000.-

2007/08

Joint Venture

Irmãos Cavaco &

OFM &

Seth

Portugal

6 months

Rhyl Flats

Offshore Windpark

06.084/128

Placing of erosion protection around 25 windmills and installation of 49 J-tubes.

2008 works: filter stone in 13 areas and Cover stone in 25 layers finally installation of 49 external J-tubes.

Depth: 7-14 m  LAT

Total turn over – Euro 1,850,000.-

2007/08

MT Højgaard

Knud Højgaards

Vej 9

DK-2860 Søborg

8 months

Burbo Wind Power Plant

England

06.098/130

Additional J-tubes and cable stone protection works.

Placed stone: 2,000 m3 filterstone and

2,500 m3 coverstone

Depth: 8-10 m  LAT

Total turn over – Euro 325,000.-

2007

MT Højgaard

Knud Højgaards

Vej 9

DK-2860 Søborg

2 months

Helgoland

Düne

Germany

07.049 / 126

Construction/reinforcement of breakwater on the Düne Island.

Quantity: 50,000 tonnes of stone.

Loaded from barge

Total turn over – Euro 650,000.-

2007

Amt für ländliche Räume Husum

Herzog-Adolf-Str. 1

D – 25813 Husum

4 months

Rødby Harbour

Denmark

07.070/127

Scour protection in connection with renovation of ferry Beth.

Total turn over – Euro 250,000.-

2007

Scandlines Denmark

Dampfærgevej 10

DK-2100 København

1 month

Lillgrund

Offshore Wind Farm

Sweden

05.071

Seabed preparation for 48 windmills and 1 transformation station.

Dredging, levelling and placing of stonebed under foundations.

Dredging: app. 75,0000 m3

Discharged ashore, distance 9 Nm

Levelling: 20,000 m2

Placed stones app. 70,500 m3

Total turn over – Euro 5,400,000.-

2006/07

Pihl Hochtief JV

Nybrovej 116

DK-2800 Kgs. Lyngby

12 months

Burbo Wind Power Plant

England

05.034/116

Placing of erosion protection around 25 windmills and installation of 47 J-tubes.

Placed stone: app. 12,000 m3

The J-tubes are installed on mono piles with divers in waters with very high current

Depth: 8-10 m  LAT

Visibility: 0 m

Total turn over – Euro 1,300,000.-

2006

MT Højgaard

Knud Højgaards

Vej 9

DK-2860 Søborg

6 months

Öckerö

Sweden

05.106/101

Capital dredging of new harbour

Quantity: 61,000 m3

Materiel: soft clay

Depth: -3.0

2005/06

Frog Dyk AB

Ringökajen

S-417 07 Göteborg

2 months

Rødby Harbour

Denmark

05.213/108

Dredging of harbour

Quantity: 35,000 m3

Materiel: sand

Depth: -8.5

Total turn over – Euro 150,000.-

2005/06

Scandlines Denmark

Dampfærgevej 10

DK-2100 København

2 months

Stralsund

Germany

05.151/100

Capital dredging of navigation channel and harbour

Quantity: 60,000 m3

Materiel: sand/clay

Depth: -7.5

Total turn over – Euro 300,000.-

2005

Heinrich Hirdes GmbH

Am Warnowkai 7B

D18147 Rostock

1½ months

Helgoland

Germany

05.095/97

Construction of new breakwater

Quantity: 12,000 tonnes of stone & 1,800 tetra pods.

Total turn over – Euro 240,000.-

2005

Nahmen Christiansen

Lüger Hörn 36

D-25980 Tinnum, Sylt

3 months

Marstal /

Ærøskøbing

Denmark

04.130/99

Capital dredging of navigation channel

Quantity: 90,000 m3

Materiel: sand/clay

Depth: -5.0 m

Total turn over – Euro 400,000.-

2005

Ærøskøbing Kommune

Statene 2

DK-5970 Ærøskøbing

4 months

Kirkwall

Orkney

Scotland

05.077/86

Capital dredging along pier at Scapa Pier and of navigation channel in Kirkwall

Quantity: 27,000 m3

Material: sand/clay

Depth:  –5.0 m.

Total turn over – Euro 170,000.-

2005

Tulloch Developments Ltd.

Bixter, Shetland

UK-ZE2 9LX

10 weeks

Kolding

Denmark

04.224/89

Capital dredging of harbour and navigation channel.

Quantity: 60,000 m3

Material: sand/mud

Depth: –2.8 to 8.0 m

Dredging and pumping

Total turn over – Euro 380,000.-

2005

Kolding Havn

Jens Holms Vej 1

DK-6000 Kolding

2 months

Kentish Flats

Wind Park

England

04.175/76

Installation of 57 J-tubes at an offshore wind farm. The J-tubes are installed on mono piles with divers in waters with high current.

Depth: about 8-10 m.

Visibility: 0 m. 

Total turn over – Euro 270,000.-

2004

MT Højgaard

Knud Højgaards

Vej 9

DK-2860 Søborg

2½ months

Hundested

Denmark

03.075/56

Maintenance dredging of navigation channel and harbour. 

Quantity: 153,000 m3.

Material: sand

Depth: -7.5 m. 

Dumped, distance 5 Nm. NNE from the harbour for beach replenishment.

Total turn over – Euro 500,000.-

2003

-

2004

Hundested Havn I/S

Amtsvejen 2

DK-3390

Hundested

4 months

Rødsand

Windmillpark

Nysted

Denmark

01.228

Dredging, levelling and scour protection for 72 windmills and 1 transformation-station.

Dredging of sand and moraine clay.

Depth: -7.0 to -13.5 m.

Dumped, distance 10 Nm. from windmill park

Quantity and size of stone: 10,220 m3 gravel (5-60 mm.), 8,760 m3 filter stone (5-60 mm.), 14,600 m3 cover stone (60-500 mm.).

Total turn over – Euro 4,700,000.-

2003

-

2002

Per Aarsleff A/S

Lokesvej 15

DK-8230 Aabyhöj

12 months

Papa Stour

Shetland Islands

03.041/47

Delivery and placing in breakwater. Dredging of 3,000 m3 sand in terminal.

Size and volume: 14,750 m3 unsorted core material, 2,350 m3 filter stone and 4,050 m3 cover stone at 2-2½ T.

Total turn over – Euro 350,000.-

2003

Tulloch Developments Ltd.

Bixter, Shetland

UK-ZE2 9LX

6 weeks

Lübeck

Germany

01.048/33

Dredging for new terminal.

Quantity: 100,000 m3

Material: sand/clay/mud

Depth: –9.5 m.

Dumped, distance 22 Nm.

Total turn over – Euro 225,000.-

2002

Combispeed

Steinbrücker-

strasse 1

D-23556 Lübeck

Germany

2 months

Gaza

Palestine

00.115/2

Dredging of 1,000 m. trench for a marine pipe. Assist with placing sea pipes and replace of excavated material around the installed pipe. A PEH pipeline 600 mm. and 400 mm. in diameter.

Total turn over – Euro 450,000.-

2001

E. Pihl & Søn A/S

Nybrovej 116

DK-2800

Kgs. Lyngby

4 months

Gosport

Portsmouth

England

99.053

Dredging of harbour and land reclamation of sand.

Quantity: 60,000 m3 sand and gravel land reclamation. 80,000 m3 dredged.

Material: clay

Depth: -2.15 m.

Dumped, distance 15 Nm.

Total turn over – Euro 1,200,000.-

2000

Gosport Marina

Momby Road

Gosport

PB12 1AH

Hampshire

22 weeks

Øresund

Denmark

96.299

Construction of 8 protection islands for the piers. Shipment and placement.

Stone size: 0-300 mm.

Quantity: about 275,000 m3 of stone from Katholm.

2000

-

1999

Sund Link Contractors I/S

Box 50114

S-20211 Malmö

8 months

Øresund

Denmark

97.011

Seabed preparation for 18 lighthouses in new navigations channel

Dredging, placing and levelling of gravel bed.

Placing of 55 km. of sea cable.   

1999

MT Højgaard

Knud Højgårds

Vej 9

DK-2860  Søborg

12 months

Bergkvara

Sweden

98.171

Dredging of harbour and navigation channel. 

Quantity: a total of 160,000 m3

Material: hard moraine clay and sand stone.

Depth: -6.10 m.  

1999

PNB Entreprenad AB

Muskötgatan 8B

Box 22286

S-25024 Helsingborg

4 months

Copenhagen

Denmark

Dredging of a navigation channel for a tunnel in Nordhavnen.

Quantity: 105,000 m3

Material: hard moraine clay.

The material was used for a new breakwater.

1997

The Sound Tunnel Contractors

Amager Strandvej 60-64

DK-2300

Copenhagen S

 

The Great Belt

Denmark

The east bridge – construction of scour protection around 18 piers.   

Placing of about 250,000T. stone.

1993-1995

Great Belt Contractos

Vester Søgade 10

DK-1601 Copenhagen V

2 years

The Great Belt

Denmark

The west bridge – construction of scour protection around 62 piers. Placing of about 1,000,000T. stone.

1991-1993

Great Belt Contractos

Vester Søgade 10

DK-1601 Copenhagen V

2 years

Halsskov

Denmark

Construction of breakwater for a temporary working harbour.

Material: stone

Quantity: 70.000 m3

1990

-

1989

MT Højgaard

Knud Højgårds

Vej 9

DK-2860 Søborg

6 months

 

 

 

 

To the top